Posted: 23/04/20

Drax Power: eAUC Case Study

Drax Power, who runs Europe’s biggest biomass-fuelled power station, used to manage their supplier service and product auctions using a combination of spreadsheets and paper-based systems.

Drax Power eAUC Case Study

This meant that auctions were not configured in a standardised format and information was difficult to locate, leading to inefficiencies within the procurement department.

They now run eAuction events using ARCUS® eAUC, a cloud-based module that encourages competitive online negotiations, leading to reduced procurement costs and improved visibility throughout the negotiation process.

Thanks to the cloud-based nature of ARCUS® eAUC, Drax Power now has the capacity to negotiate with more suppliers on a global scale and on a real-time basis.

You can download the Drax Power case study by completing the short form below.

Download Case Study...